Baekke School

Baekke, DK

Before Commissioning
Electricity Consumption: 128,000 kWh/a
Heat Consumption: 431,000 kWh/a
Energy Solution 1 x XRGI® 20
Additional Systems: 1.0000 Storage Tank
14 kW Heat Pump
Boiler
Commissioning: 2019
After Commissioning
Electricity Coverage: 65%
Heat Coverage: 100%
--- XRGI®: 61%
--- Heat Pump: 39%
--- Boiler: 0%
Energy Reduction: 23%
Cost Reduction: $21,032/a
Carbon Reduction: 29%
ECP Icons blue transparent Education
download svg
download svg

School Solms

Solms, DE

Before Commissioning
Electricity Consumption: 200,000 kWh/a
Heat Consumption: 1,100,000 kWh/a
Energy Solution XRGI® 20
Premium Partner: WHSE GmbH & Co. KG
Commissioning: 2017
After Commissioning
Generated Electricity: 100,000 kWh/a
Electricity Consumption: 75,000 kWh/a
Electricity Coverage: 38%
Generated Heat: 200,000 kWh/a
Heat Coverage: 18%
Cost Reduction: $15,336/a
Carbon Reduction: 36 t CO2/a
ECP Icons blue transparent Education
download svg
download svg

Joerlunde Educational Centre

Copenhagen, DK

Before Commissioning
Electricity Consumption: 941,000 kWh/a
Heat Consumption: 1,239,000 kWh/a
Energy Solution 3 x XRGI® 20
Additional Systems: 2 x 1,000L Storage Tank
57 kW Heat Pump
Boiler
Commissioning: 2016
After Commissioning
Electricity Coverage: 34%
Heat Coverage: 100%
--- XRGI®: 66%
--- Heat Pump: 21%
--- Boiler: 13%
Energy Reduction: 64%
Cost Reduction: $69,013/a
Carbon Reduction: 23%